How Much Concrete for a 10×20 Slab at 4 Inches?

A 10 ft × 20 ft slab 4 inches thick needs this much concrete — cubic yards and bag counts, calculated for you. Here is the answer, plus a calculator you can adjust if your measurements are slightly different.

Answer: 2.47 cubic yards

How it changes with thickness

Same area, different thickness:

Thickness456
Concrete needed2.47 cubic yards3.09 cubic yards3.70 cubic yards
80 lb bags112 bags139 bags167 bags

What a 10×20 slab at 4 inches actually involves

This is the awkward middle: too big to enjoy mixing by hand — 112 bags is roughly 4.9 tons to carry and open — but small enough that a ready-mix supplier will add a short-load surcharge for sending a truck. Most people at this size either hire a drum mixer and do it in a day with three or four people, or pay the surcharge and take the easy route. Decide before you order, because you cannot change your mind halfway through a pour.

The slab is 200 ft² and, at 4 inches thick, takes 66.67 ft³ of concrete — 2.47 yd³, weighing about 4.9 tons. Everything below is worked out from those figures.

Full material list

ItemQuantityNotes
Concrete2.47 yd³112 × 80 lb bags, or 149 × 60 lb bags
Gravel base2.96 yd³order loose for 4 in compacted; see the gravel calculator
Form lumber66 lin ft2×4 or 2×6, includes 10% waste
Form stakes15roughly one every 4 ft of perimeter
Welded wire mesh5 sheets5×10 ft sheets of 6×6-W1.4 mesh, 10% overlap
Vapor barrier220 ft²about 23 lin ft of 10 ft wide roll
Control joints3 joints40 lin ft of saw cut

Control joints and cracking

Control joints stop a slab cracking wherever it likes. The conservative rule is to space them at twice the slab thickness in inches — here that means every 8 ft, which divides this slab into 2 × 3 panels of roughly 5.0 × 6.7 ft. That is 3 joints, about 40 linear ft of cutting. Get them in while the concrete is still green, typically 6 to 12 hours after finishing, before random cracks get there first.

Reinforcement at 4 inches

At 4 in, 5 sheets of 6×6-W1.4 welded wire mesh on chairs is the standard reinforcement. Lap the sheets about 6 in and keep them at mid-depth, so the steel ends up in the middle of the slab rather than resting on the sub-base. Mesh does not stop cracks forming — it holds them tight after they do, which is exactly what you want in a patio or shed floor. If this slab will take vehicles, step up to 5 or 6 in and use rebar instead.

Bagged concrete or a ready-mix truck?

OptionQuantityEstimated cost
Bagged 80 lb112 bags$672
Ready-mix delivered2.47 yd³ + short-load fee$510

On these assumptions ready-mix is cheaper ($510 vs $672) as well as far less work. It only wins if the truck can actually reach the site and you can place the whole load without stopping. If access is a problem, bagged at $672 is the practical fallback and lets you pour in stages.

Costs assume $6 per 80 lb bag, $170 per cubic yard delivered, and a $90 short-load surcharge below 5 yd³. Ready-mix pricing moves with region, season and fuel, so treat these as a starting point for calling suppliers rather than a quote.

Pour day, in order

  1. Excavate to 8 in below finished grade: 4 in of slab plus 4 in of base.
  2. Spread the base in two lifts and compact each one. Rent a plate compactor; a hand tamper leaves soft spots that crack later.
  3. Set the forms to 4 in, level and square, staked every 4 ft.
  4. Lay the vapor barrier with 6 in laps, then the mesh on chairs so it ends up mid-depth rather than resting on the ground.
  5. Set up the mixing station before you open a bag: water, hose, wheelbarrow or drum mixer, and a place to dump. Mix only what you can place within about 20 minutes.
  6. Place, screed and float in one continuous run. A batch that sits while you fetch something is a batch you will be fighting later.
  7. Cut or tool the control joints while the concrete is still green, aiming for 6 to 12 hours after finishing. You need about 40 linear ft of cutting.
  8. Cover it and keep it damp for 7 days. Full design strength arrives at 28 days.

Local codes cover frost depth, reinforcement and permits, and they vary from place to place. Check with your local building department before you dig or pour.

Common questions

How many bags of concrete for a 10×20 slab at 4 inches?

112 bags of 80 lb mix, or 149 bags of 60 lb mix. A 10×20 slab at 4 in is 66.67 ft³, which is 2.47 yd³. An 80 lb bag yields about 0.60 ft³ and a 60 lb bag about 0.45 ft³, so divide the volume by the yield and round up.

How much does a 10×20 concrete slab cost?

Roughly $672 in 80 lb bags, or about $510 delivered as ready-mix, which includes a short-load surcharge because the order is under 5 cubic yards. Material only — it excludes excavation, base, reinforcement and labour.

How thick should a 10×20 slab be?

Four inches for a patio, shed floor or footpath. Five to six inches if vehicles will drive on it. This page is worked through at 4 inches, so switch the calculator above to compare thicknesses.

How much gravel goes under a 10×20 slab?

About 2.96 yd³ of loose crushed base for a 4 in compacted layer, covering 200 ft². Order it loose rather than already compacted — the material settles by roughly a fifth under a plate compactor.